MOB-13 — Field test with a delegate — GPS, weak network, offline

A real tour in Oran-like conditions: tolerance, airplane-mode visits and sync recovery, photo queue, battery drain measured.

FieldDetails
Task codeMOB-13
PhaseP1 — V1 build & integration
Product scopeV1
StatusPlanned
StartThu 17 Dec 2026
DueMon 21 Dec 2026
ResponsibleImad — Mobile developer (Flutter)
Co-responsibleAkram
Effort1.5 person-day(s) planned · 3 from scratch · size S
Area · appMobile quality · mobile
Depends onMOB-12
UnblocksMOB-14
Milestones—

Summary

A real tour in Oran-like conditions: tolerance, airplane-mode visits and sync recovery, photo queue, battery drain measured.

Description

Lab tests do not reproduce shops with thick walls, 3G in town centres or a full day on battery; this task runs a real tour with a delegate in Oran-like conditions to validate tolerance, offline behaviour and battery before the stores (SYN-04, SYN-05, FLD-07, FLD-15). Scope: one real tour of 8–12 points of sale on staging or pre-production data, with Imad observing the app and Akram observing usability and outdoor readability: check-in distance and accuracy per stop, airplane-mode visits and sync recovery, the photo queue on weak networks, and battery drain with sampling. Out of scope: building new features; fixes found go into MOB-15/MOB-17 or hot fixes. It needs a pilot delegate and real point-of-sale coordinates arranged with HOCO, a tour planned in the back-office, and the MOB-12 build. The findings tune the tolerance and sampling defaults proposed to Anis and feed MOB-14 and DQA-03.

Subtasks

#SubtaskOwner
1Plan the field day with HOCO: delegate, 8–12 real points of sale with verified coordinates, tour created in the back-office, test resellers preparedImad
2Measurement sheet per stop: time to fix, accuracy, distance at check-in, tolerance result, indoor vs outdoorImad
3Offline scenario: three consecutive visits in airplane mode (with photos and a new prospect), then reconnection and sync timingImad
4Weak-network scenario: photo queue on 3G/EDGE with progress and retry observedImad
5Battery and data measurement over the tour with sampling on (batterystats, data usage)Imad
6Usability and outdoor readability observation (sunlight, one-handed use, gloves/fast taps), notes with photosAkram
7Debrief with the delegate and written findings, prioritised as blocker / fix before pilot / laterAkram
8Proposals to Anis for tolerance, accuracy and sampling defaults based on the measurementsImad

Deliverables

  • Field test report (metrics per stop, offline and battery results, findings) shared with Anis and Akram
  • GitHub issues for each finding labelled field-test with priority
  • Proposed field settings values (tolerance, accuracy, interval, distance)

Acceptance criteria

  • All visits of the day are on the server after sync with zero duplicates and zero lost photos (SYN-05)
  • At least 90 % of check-ins at correctly located stores pass the 150 m tolerance; every failure is explained (wrong coordinates, indoor accuracy) (FLD-07)
  • Offline visits replay within 1 minute of reconnection (SYN-04)
  • Battery drain over the tour is measured and within the agreed target, or a mitigation is planned (FLD-15)
  • No crash or ANR during the tour (Sentry clean for the session)

Requirements covered

RequirementTitleRelease
SYN-04Delegate app keeps the tour, visits, notes and photos locally under weak networkV1
SYN-05Sync queue handling retries, duplicates (idempotency), errors and conflictsV1
FLD-07Map and navigation: position, next destination with ETA and distance, external GPS navigation, arrival confirmation within toleranceV1
FLD-15Location policy: consent, frequency, tolerance and retention configurable and transparentV1

Test measures

  • Real tour with a delegate following the measurement sheet
  • Post-tour server audit: visits, photos, pings and prospects compared with the app's local logs
  • Sentry and battery stats review of the field devices

Risks

  • Bad weather, delegate unavailability or wrong store coordinates waste the day — book a backup date and verify coordinates the day before
  • Testing on staging with real shop owners may confuse them — use test resellers or brief the visited shops in advance with HOCO

KPI

  • Delivered by Mon 21 Dec 2026 within 1.5 person-day(s).
  • Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
  • Zero open critical defects, permission gaps or data-integrity regressions at sign-off.

Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.