Imad — Mobile developer (Flutter)

Every task assigned to Imad, with dates, dependencies and briefs.

Owns: Reseller app and delegate app (Flutter monorepo)

Load: 44 open tasks · 69.75 person-days at 1 FTE. Each task links to a full brief: description, subtasks, deliverables, acceptance criteria, requirements, screens, API and tests.

18 Oct 2026 → 31 Jan 2027
Oct 2026Nov 2026Dec 2026Jan 2027Feb 202718/1025/101/118/1115/1122/1129/116/1213/1220/1227/123/110/117/124/131/1
Milestones
P1 — V1 build & integration
P2 — Acceptance, go-live & pilot
P3 — Generalisation (after the 3 months)
ImadV2 scopePublic holiday◆ Milestone (hover for name)

P0 — Foundations (cadrage, UX/UI, architecture & contract)

TaskNamePhaseDatesEffortDepends on
MOB-01Flutter monorepo — workspace, two apps, flavors, CIP0Sun 18 Oct1 d—
MOB-02Core package — HTTP client, interceptors, errors, storage, loggingP0Mon 19 Oct1 dMOB-01
MOB-07Localisation & formattingP0Tue 20 Oct0.5 dMOB-01
MOB-04Flutter design system — tokens, theme, componentsP0Wed 21 Oct → Sun 25 Oct2.5 dDES-03, MOB-01
MOB-03API client from the OpenAPI contract + mock server workflowP0Sun 25 Oct → Mon 26 Oct1 dSRV-03, MOB-02
MOB-05Navigation, app shells & system statesP0Mon 26 Oct → Tue 27 Oct0.75 dMOB-04
MOB-06Authentication flows (both apps)P0Tue 27 Oct → Wed 28 Oct1.75 dMOB-03, MOB-05, DES-06
MOB-08Push notifications foundationP0Thu 29 Oct0.75 dMOB-06
MOB-09Offline foundation for the delegate app (local DB + outbox sync)P0Thu 29 Oct → Wed 04 Nov2.5 dMOB-03
MOB-10Location, maps & consent foundationP0Wed 04 Nov → Thu 05 Nov1.25 dMOB-05
MOB-11Media capture & uploadsP0Thu 05 Nov → Sun 08 Nov0.75 dMOB-03

11 tasks · 13.75 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P1 — V1 build & integration

TaskNamePhaseDatesEffortDepends on
MRA-01Reseller app — homeP1Sun 08 Nov → Mon 09 Nov1.25 dMOB-06, DES-07
MRA-02Reseller app — catalog, search, scanner, filtersP1Mon 09 Nov → Wed 11 Nov2 dDES-07
MRA-03Reseller app — product detail & favoritesP1Wed 11 Nov → Thu 12 Nov0.75 dDES-08
MRA-04Reseller app — cart, checkout & confirmationP1Thu 12 Nov → Sun 15 Nov1.5 dDES-08
MRA-05Reseller app — orders, tracking & assisted-order confirmationP1Sun 15 Nov → Tue 17 Nov1.5 dDES-09
MRA-06Reseller app — promotions & daily offersP1Tue 17 Nov0.75 dDES-10
MRA-07Reseller app — account, store, finance & settingsP1Wed 18 Nov → Thu 19 Nov1.25 dDES-10, DES-09
MRA-08Reseller app — notifications & supportP1Thu 19 Nov → Sun 22 Nov1.25 dMOB-08, DES-10
MRA-09Reseller app — invitation attributionP1Sun 22 Nov → Mon 23 Nov0.75 dMOB-06
MRA-10Reseller app — returns & live order updatesP1Mon 23 Nov → Tue 24 Nov1 dMRA-05
MRA-11Reseller app — Notification Centre, action buttons, group preferences, promotion tabs & flash-sale countdownP1Tue 24 Nov → Wed 25 Nov1.5 dMRA-06, MRA-08, MRA-10, DES-23, SRV-39
MDA-01Delegate app — home, profile, zone, objectivesP1Wed 25 Nov → Thu 26 Nov1.25 dDES-11, MOB-09
MDA-02Delegate app — tour programme & calendarP1Sun 29 Nov → Mon 30 Nov1.5 dDES-12
MDA-03Delegate app — map, navigation & arrival check-inP1Mon 30 Nov → Tue 01 Dec1.25 dDES-12, MOB-10
MDA-04Delegate app — point-of-sale sheet & prospects listP1Tue 01 Dec → Wed 02 Dec1.25 dDES-13
MDA-05Delegate app — visit flowP1Thu 03 Dec → Sun 06 Dec1.5 dDES-13, MOB-11
MDA-06Delegate app — visit report & follow-upsP1Sun 06 Dec → Mon 07 Dec1.25 dDES-13
MDA-07Delegate app — new reseller (offline) & editP1Mon 07 Dec → Tue 08 Dec1.25 dDES-14
MDA-08Delegate app — invitation (QR, share, tracking)P1Wed 09 Dec0.75 dDES-14
MDA-09Delegate app — first-order assistance & ordersP1Wed 09 Dec → Thu 10 Dec1.25 dDES-14, MRA-04
MDA-10Delegate app — tour closing, reports & performanceP1Sun 13 Dec → Mon 14 Dec1.25 dDES-14
MDA-11Delegate app — messages, settings & sync centreP1Mon 14 Dec0.75 dDES-14, MOB-09
MDA-12Delegate app — location sampling during toursP1Tue 15 Dec0.75 dMOB-10
MOB-12Staging integration — real API, edge states, performanceP1Tue 15 Dec → Thu 17 Dec2 dMDA-12, SRV-23, SRV-18, SRV-19, SRV-24, SRV-26
MOB-13Field test with a delegate — GPS, weak network, offlineP1Thu 17 Dec → Mon 21 Dec1.5 dMOB-12
MOB-14Store readiness — Play Console tracks, data safety, location declarationP1Mon 21 Dec → Tue 22 Dec1 dMOB-13, DQA-01
MOB-15Mobile test automation & hardeningP1Tue 22 Dec → Thu 24 Dec2 dMOB-14
MOB-17Design QA fixes & accessibility pass (both apps)P1Thu 24 Dec → Sun 27 Dec1.5 dDQA-03, MOB-15

28 tasks · 35.5 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P2 — Acceptance, go-live & pilot

TaskNamePhaseDatesEffortDepends on
LCH-03BPilot (2 weeks) — mobile support & hotfixes (Imad)P2Thu 31 Dec → Thu 14 Jan10 dLCH-02

1 tasks · 10 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P3 — Generalisation (after the 3 months)

TaskNamePhaseDatesEffortDepends on
MOB-18Pilot improvements — mobileP3Sun 17 Jan → Tue 19 Jan3 dLCH-03B
MOB-16iOS build & App Store release (on client decision)P3Wed 20 Jan → Sun 24 Jan3 dMOB-18

2 tasks · 6 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P4 — V2 evolutions

TaskNamePhaseDatesEffortDepends on
MRA-20V2 — Reseller app loyalty, rewards & packs V2P4Mon 25 Jan → Wed 27 Jan3 dSRV-29, DES-30
MDA-20V2 — Optimised routes & field analytics in the delegate app V2P4Thu 28 Jan → Sun 31 Jan1.5 dMRA-20

2 tasks · 4.5 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.