LCH-03B — Pilot (2 weeks) — mobile support & hotfixes (Imad)

Two calendar weeks on call for pilot users: crash/ANR triage, hotfix releases on the closed track, field visits with delegates when needed.

FieldDetails
Task codeLCH-03B
PhaseP2 — Acceptance, go-live & pilot
Product scopeV1
StatusPlanned
StartThu 31 Dec 2026
DueThu 14 Jan 2027
ResponsibleImad — Mobile developer (Flutter)
Co-responsible—
Effort10 person-day(s) planned · 10 from scratch · size L
Area · appLaunch · mobile
Depends onLCH-02
UnblocksMOB-18
MilestonesPilot go / no-go

Summary

Two calendar weeks on call for pilot users: crash/ANR triage, hotfix releases on the closed track, field visits with delegates when needed.

Description

During the two-week pilot a limited group of delegates and resellers uses the production apps for real work, and mobile issues must be caught and fixed before generalisation (OPS-06). Scope: Imad is on call for the pilot users — crash and ANR triage from Sentry and Play vitals, sync-error follow-up per delegate, hotfix releases on the closed track with a forced update when needed, and field visits with delegates when a problem cannot be reproduced remotely. New features are out of scope; improvements are logged for MOB-18. It needs from Anis the production monitoring (server logs, sync errors per delegate), a daily 15-minute triage slot and AppVersionPolicy changes for forced updates; Akram joins field visits for UX observation when useful. The pilot findings become the MOB-18 backlog and feed LCH-05.

Subtasks

#SubtaskOwner
1On-call rota for the pilot (Sunday–Thursday working hours, Africa/Algiers, plus a best-effort weekend channel) and a pilot users' support channelImad
2Alerting: Sentry alerts on new issues and crash-free sessions below 99.5 %, Play Console vitals (ANR, crash rate) checked dailyImad
3Daily triage with Anis: crashes, sync rejections per delegate (VISIT_LOCKED, PHONE_ALREADY_EXISTS, OCCURRED_AT_OUT_OF_RANGE), failed check-ins, checkout errorsAnis
4Hotfix process: hotfix/<id> branch from the release tag, version bump, CI suites green, closed-track release with notes, merge back to devImad
5Forced update through AppVersionPolicy when a hotfix fixes data loss or sync corruptionAnis
6Field visits with pilot delegates (first days and on demand) to observe tours, check-ins and sync in real shopsImad
7UX observations during field visits feeding the MOB-18 backlogAkram
8Pilot log: incidents, fixes, versions released, open feedback, prioritised for MOB-18Imad

Deliverables

  • Hotfix releases 1.0.x of the affected app(s) on the closed track with release notes
  • Pilot log (incidents, root causes, fixes, feedback) shared with Anis and Akram
  • Prioritised MOB-18 backlog as GitHub issues labelled pilot

Acceptance criteria

  • Every crash or ANR reported during the pilot is triaged within one working day and either fixed or scheduled with a reason
  • Crash-free users stay at or above 99.5 % for both apps over the pilot (target to confirm in the acceptance plan)
  • At the end of each pilot day no delegate has unresolved sync errors without an explanation (SYN-05 in production)
  • Every hotfix ships through CI and the closed track with notes, never as a side-loaded APK
  • The pilot log and the MOB-18 backlog are ready for the pilot retrospective

Requirements covered

RequirementTitleRelease
OPS-06Pilot with a limited group of delegates and resellers, then progressive generalisationV1

Test measures

  • Full integration_test suites run before each hotfix release
  • Smoke test of each hotfix on two pilot devices before promoting it
  • Post-pilot review of Sentry release health per version

Risks

  • A hotfix introduces a regression in offline sync — sync suites mandatory before release and staged rollout to a few delegates first
  • Pilot delegates stay on old versions — minimum version raised through AppVersionPolicy after each critical hotfix

KPI

  • Delivered by Thu 14 Jan 2027 within 10 person-day(s).
  • Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
  • Zero open critical defects, permission gaps or data-integrity regressions at sign-off.

Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.