Requirements OPS-01 to OPS-06: environments, deployment, training, maintenance and support, acceptance and the pilot, within the three-month V1 frame.

This area covers how V1 reaches production and is run (cahier §12, §13, §14). Binding frame (AUTHORING §1): design, development and deployment of V1 take three months from 18 Oct 2026; V1 — including the reseller web — goes to production at the start of January 2027, followed by a two-week pilot; generalisation and V2 come after the three months. Dates come from the plan: see the timeline. Owner: Anis for DevOps, with Imad for the stores and Akram for training material. Technical details: deployment and operations.

IDRequirementReleasePrioritySourceApps
OPS-01Three environments: development, pre-production (client acceptance), productionV1MUST§13.1OPS
OPS-02Deployment: server, database, storage, backups, domains, certificates, external services, store publicationV1MUST§13.2OPS
OPS-03Training: administrators and managers, delegates on a full tour scenario, reseller quick guide, admin documentation and support proceduresV1MUST§13.3OPS
OPS-04Maintenance: warranty period, corrective/preventive/evolutive maintenance, support SLAs and priorities, monitoring and security updatesV1MUST§13.4OPS
OPS-05Acceptance: priority scenarios pass, blocking defects fixed, acceptance report (PV) signedV1MUST§12OPS
OPS-06Pilot with a limited group of delegates and resellers, then progressive generalisationV1MUST§14OPS

3-month frame: design → development → deployment — deadline 17 Jan 2027.

DateMilestoneTargetReached when these tasks end
18 Oct 2026Cadrage validated — validation sheet signed—PRJ-03
18 Oct 2026API contract v1 published (OpenAPI + mock server)—SRV-03
19 Oct 2026Server V1 feature-complete—SRV-26, SRV-40
21 Oct 2026Design system v1 ready (tokens + components)—DES-04
22 Oct 2026Screen inventory frozen—DES-05
29 Oct 2026Reseller app designs ready for client review—DES-10
05 Nov 2026Delegate app designs ready for client review—DES-14
08 Nov 2026Mobile foundations ready—MOB-11
12 Nov 2026Back-office designs ready for client review—DES-19
16 Nov 2026Design handoff complete—DES-21
03 Dec 2026Back-office and reseller web V1 feature-complete—DSH-12, WEB-05, WEB-06
15 Dec 2026Mobile apps V1 feature-complete—MDA-12
22 Dec 2026Staging integration complete—MOB-14, SRV-28
28 Dec 2026Acceptance report (PV de recette) signed—QA-02
29 Dec 2026Production go-liveon time — 17 Jan 2027LCH-01
30 Dec 2026Pilot startson time — 17 Jan 2027LCH-02
14 Jan 2027Pilot go / no-go—LCH-03, LCH-03B
21 Jan 2027Generalisation complete—LCH-05
22 Feb 2027V2 delivered—SRV-38, DSH-21, MDA-20, WEB-20, DQA-12

OPS-01 — Environments

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §13.1OPSOPS-01, OPS-02

Statement — The system shall run in separate development, pre-production (client acceptance) and production environments.

Rules

  1. Environments: local (docker compose), staging (auto-deployed from dev, team integration), pre-production / recette (release candidates, HOCO's acceptance), production (tags on master). The cahier's three environments map to local + staging (development), pre-production and production.
  2. Each environment has its own database, storage buckets, secrets, Firebase project and app flavor, maps keys and domains (api-staging.hoco.dz, …; D-12).
  3. Production personal data is never copied to other environments without anonymisation; providers run in simulator or sandbox mode outside production.

Acceptance criteria

  • A build tagged on master deploys only to production; a staging app cannot authenticate against production.

Data — none.

Interfaces — none.

OPS-02 — Deployment

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §13.2OPSOPS-02, LCH-01, MOB-14, DQA-01

Statement — The team shall deploy and configure the server, database, storage, backups, domains, certificates, external services and store publication.

Rules

  1. Go-live checklist: server, back-office and reseller web on Dokploy with TLS; database migrations applied after a backup; storage buckets and lifecycle rules; nightly backups verified and one restore done; domains and DNS; provider accounts in HOCO's name (INT-07); monitoring and alerts live (NFR-08); initial imports of products, resellers, users and stock (ADM-06); invitation landing and app-link files live.
  2. Stores: both Android apps on the Play closed track for pilot users at go-live, public track at generalisation; data-safety form, location declaration, privacy policy and store assets ready (MOB-14, DQA-01). iOS only on D-10.
  3. Releases outside 08:00–18:00 Sunday–Thursday, downtime under 5 minutes, documented rollback (previous image + backup).

Acceptance criteria

  • The go-live checklist is signed with every item checked; pilot users install both apps from the closed track and use the reseller web on production.

Data — all.

Interfaces — none.

OPS-03 — Training

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §13.3OPSLCH-02, LCH-05, DQA-06

Statement — The team shall train administrators and managers, train delegates on a complete tour scenario, provide a reseller quick guide, and hand over administration documentation and support procedures.

Rules

  1. Before the pilot: back-office sessions per role (commercial, stock, finance, delivery, direction); pilot delegates trained on a full tour (start, navigation, check-in, visit, report, sign-up, invitation, assisted order, offline, closing); reseller quick guide (PDF and in-app link) for pilot resellers covering the app and the web.
  2. At generalisation: remaining delegates trained wave by wave (LCH-05).
  3. Materials in French (DQA-06): reseller guide, delegate field guide, back-office quick-reference cards; this docs site is the administration reference; support procedures say who handles what and how to escalate.
  4. Attendance recorded; every trained delegate completes one tour on pre-production or in the pilot.

Acceptance criteria

  • Every pilot delegate has an attendance record and closed a full training tour; the support procedure is handed to HOCO.

Data — none.

Interfaces — none.

OPS-04 — Maintenance and support

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §13.4OPSLCH-04, LCH-05, MOB-18

Statement — Maintenance shall define a warranty period, corrective, preventive and evolutive maintenance, support delays and priorities, and monitoring and security updates.

Rules

  1. Warranty: corrective maintenance included for a period to specify in the contract (decided: 2 months after go-live).

  2. Priorities and targets (proposal, working hours Sunday–Thursday):

    PriorityExampleResponseFix or workaround
    P1 blockingAPI down, orders or check-ins impossible2 h1 working day
    P2 majora feature broken without workaround1 working day5 working days
    P3 minorcosmetic, workaround exists3 working daysnext release
    P4 evolutionnew need—backlog, quoted
  3. Preventive: monthly dependency and OS updates, critical security fixes within 7 days, certificate and backup checks, quarterly restore test.

  4. Evolutive work follows the change process (D-38 for what moves after go-live).

Acceptance criteria

  • The maintenance terms (warranty, priorities, delays) are in the signed contract; the monthly update log exists after go-live.

Data — none.

Interfaces — none.

OPS-05 — Acceptance (recette)

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §12OPSQA-01, QA-02, QA-03

Statement — V1 shall be accepted when the priority scenarios pass, blocking defects are fixed and the acceptance report (PV) is signed.

Rules

  1. Priority scenarios of §12: reseller account, catalog, order, stock, tracking, promotion, loyalty, tour, GPS, prospect, invitation, first order, report, permissions, offline. Loyalty is V2: its scenario is deferred and noted in the PV; the others are executed on the reseller app, the reseller web, the delegate app and the back-office (acceptance scenarios).
  2. Sequence: team integration tests on staging (QA-01) and scripted functional campaign (QA-03), then HOCO's acceptance on pre-production (QA-02).
  3. Exit: every V1 priority scenario passed, 0 open blocking (P1) defects, major (P2) defects with an agreed workaround and date, PV signed — milestone Acceptance report signed, before Production go-live.

Acceptance criteria

  • The signed PV lists each scenario with its result on each app and the open defects with their priority.

Data — none.

Interfaces — none.

OPS-06 — Pilot then progressive generalisation

ReleasePrioritySourceAppsOwner tasks
V1MUSTcahier §14OPSLCH-03, LCH-04, LCH-05, LCH-03B, DQA-08, MOB-18

Statement — After go-live, V1 shall run for two weeks with a limited group of delegates and resellers, then open progressively.

Rules

  1. Pilot group (proposal, D-32): 3 to 5 delegates in one or two zones and their 30 to 60 resellers, using the apps and the reseller web; two calendar weeks right after the January go-live, before Ramadan.
  2. Daily triage of defects and KPIs, hotfixes on the closed track and production (LCH-03, LCH-03B); UX observation in the field (DQA-08).
  3. Go / no-go criteria (proposal): no open P1; crash-free sessions ≥ 99 %; ≥ 99 % of queued sync items applied without manual action; ≥ 80 % of check-ins within tolerance (input for D-06); orders processed end to end from every channel.
  4. Generalisation after the three months: waves by zone with training, public store track (LCH-05); pilot improvements first (LCH-04, MOB-18).

Acceptance criteria

  • A go / no-go report with the measured criteria is signed by HOCO at the end of the pilot (milestone Pilot go / no-go).

Data — analytics aggregates (ANA-04).

Interfaces — none.