LCH-04 — Pilot improvements — server & back-office

Prioritised fixes and adjustments from the pilot retrospective; decision log updated.

FieldDetails
Task codeLCH-04
PhaseP3 — Generalisation (after the 3 months)
Product scopeV1
StatusPlanned
StartThu 14 Jan 2027
DueTue 19 Jan 2027
ResponsibleAnis — Full-stack developer
Co-responsible—
Effort3 person-day(s) planned · 8 from scratch · size M
Area · appLaunch · shared
Depends onLCH-03
UnblocksLCH-05
Milestones—

Summary

Prioritised fixes and adjustments from the pilot retrospective; decision log updated.

Description

The pilot (LCH-03) produces a prioritised list of fixes and adjustments; this task delivers the server and back-office part before generalisation (OPS-04, OPS-06). Typical items are ergonomics of the confirmation queue and order detail, tuning of settings closed in PRJ-03 (GPS tolerance, minimum amounts, return window, assisted-order expiry), report and KPI adjustments requested by direction, performance fixes found under real load, notification wording, and data corrections from the initial import. Each change is classified as a setting change or a code change, recorded in the decision log, tested and released to production. Out of scope: new V2 features and mobile changes (Imad's pilot improvements).

Subtasks

#SubtaskOwner
1Turn the pilot report into a prioritised backlog with HOCO (must before generalisation / later)Anis
2Settings adjustments with before/after values recorded in the decision logAnis
3Back-office ergonomics fixes (confirmation queue, order detail, CRM validation, tour planner) from pilot feedbackAnis
4Server fixes and performance improvements found under real load (queries, indexes, job timings)Anis
5Report and KPI adjustments requested by directionAnis
6Notification template wording and rule adjustmentsAnis
7UI adjustments review for changed back-office screensAkram
8Release to production with changelog and regression runAnis

Deliverables

  • Prioritised pilot backlog (GitHub milestone LCH-04)
  • Production release with changelog
  • Updated decision register and settings values

Acceptance criteria

  • Every item marked must-before-generalisation is released to production (OPS-06)
  • Every changed setting has an entry in the decision log and in the activity log
  • The regression suite passes on the released version
  • HOCO confirms the release closes the pilot findings

Requirements covered

RequirementTitleRelease
OPS-04Maintenance: warranty period, corrective/preventive/evolutive maintenance, support SLAs and priorities, monitoring and security updatesV1
OPS-06Pilot with a limited group of delegates and resellers, then progressive generalisationV1

Test measures

  • Regression suite (server tests and Playwright) before release
  • Targeted re-tests of each fixed pilot finding with the reporter

Risks

  • Scope creep from pilot wishes — anything not blocking generalisation goes to the V2 backlog with HOCO's agreement

KPI

  • Delivered by Tue 19 Jan 2027 within 3 person-day(s).
  • Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
  • Zero open critical defects, permission gaps or data-integrity regressions at sign-off.

Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.