QA-02 — Client acceptance (recette) on pre-production & PV
HOCO executes the acceptance scenarios on pre-production; blocking defects fixed; acceptance report signed.
| Field | Details |
|---|---|
| Task code | QA-02 |
| Phase | P2 — Acceptance, go-live & pilot |
| Product scope | V1 |
| Status | Planned |
| Start | Thu 24 Dec 2026 |
| Due | Mon 28 Dec 2026 |
| Responsible | Anis — Full-stack developer |
| Co-responsible | Imad |
| Effort | 2 person-day(s) planned · 5 from scratch · size M |
| Area · app | Quality · shared |
| Depends on | QA-01 |
| Unblocks | LCH-01 |
| Milestones | Acceptance report (PV de recette) signed |
Summary
HOCO executes the acceptance scenarios on pre-production; blocking defects fixed; acceptance report signed.
Description
The cahier requires a client acceptance (recette) where HOCO executes the priority scenarios, blocking defects are fixed and an acceptance report (PV) is signed (§12; OPS-05). This task deploys a release candidate to pre-production, prepares realistic data (a sample of HOCO's products with their three prices, test resellers of each customer type, delegates and a tour), provides French test scripts and test accounts, supports HOCO's testers, fixes blocking defects in the release branch with RC redeploys, and obtains the signed PV that gates production go-live. Imad provides the mobile builds pointing to pre-production. Out of scope: production deployment (LCH-01).
Subtasks
| # | Subtask | Owner |
|---|---|---|
| 1 | Cut release/x.y.z, deploy RC to pre-production, freeze scope | Anis |
| 2 | Prepare recette data: products sample with three prices and attributes, resellers per customer type, delegates, tours, support regions | Anis |
| 3 | French test scripts per scenario with expected results and a defect form | Anis |
| 4 | Mobile builds (reseller and delegate) on the Play internal track pointing to pre-production | Imad |
| 5 | Kick-off session with HOCO testers and daily follow-up during the recette | Anis |
| 6 | Fix blocking defects in the release branch, redeploy RC, re-test with HOCO | Anis |
| 7 | Mobile blocking defect fixes and rebuilds | Imad |
| 8 | Acceptance report (PV de recette) with scenario results, accepted reservations and signatures | Anis |
Deliverables
- Pre-production environment running the release candidate
- Test scripts (French) and test accounts handed to HOCO
- Signed PV de recette stored with the project records
Acceptance criteria
- HOCO executed every priority scenario on pre-production (OPS-05)
- No blocking defect remains open at signature; reservations are listed with dates
- The PV is signed by HOCO's representative
- The RC that was accepted is the one tagged for production
Requirements covered
| Requirement | Title | Release |
|---|---|---|
| OPS-05 | Acceptance: priority scenarios pass, blocking defects fixed, acceptance report (PV) signed | V1 |
Test measures
- Smoke test of pre-production after each RC redeploy
- Re-run of the scenarios linked to each fixed blocking defect
Risks
- HOCO testers unavailable or late — fixed recette window agreed in PRJ-03 and a daily slot with a named tester
KPI
- Delivered by Mon 28 Dec 2026 within 2 person-day(s).
- Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
- Zero open critical defects, permission gaps or data-integrity regressions at sign-off.
Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.
QA-01 — End-to-end integration testing on staging
Run the 15 priority acceptance scenarios of the cahier across the four apps on staging with real devices; triage and fix.
LCH-01 — Production go-live — deploy, import data, monitoring
Production deploy, initial import of products/resellers/users, monitoring and alerting live, apps published on the Play closed track for pilot users.