LCH-05 — Generalisation roll-out — waves by zone, public store release
Progressive opening zone by zone after the pilot, remaining delegates trained, apps promoted to the public Play track, maintenance and support procedures handed over.
| Field | Details |
|---|---|
| Task code | LCH-05 |
| Phase | P3 — Generalisation (after the 3 months) |
| Product scope | V1 |
| Status | Planned |
| Start | Wed 20 Jan 2027 |
| Due | Thu 21 Jan 2027 |
| Responsible | Anis — Full-stack developer |
| Co-responsible | Imad, Akram |
| Effort | 1.5 person-day(s) planned · 4 from scratch · size S |
| Area · app | Launch · shared |
| Depends on | LCH-04, MOB-18 |
| Unblocks | SRV-29 |
| Milestones | Generalisation complete |
Summary
Progressive opening zone by zone after the pilot, remaining delegates trained, apps promoted to the public Play track, maintenance and support procedures handed over.
Description
After the pilot improvements, the platform opens progressively to all zones (cahier §14; OPS-03, OPS-04, OPS-06). This task plans and runs the generalisation waves by zone (delegates trained, resellers imported or invited, capacity watched per wave), promotes both apps from the Play closed track to the public track, launches the reseller web at app.hoco.dz with links from the app, invitations and HOCO's channels, and hands over maintenance and support: SLAs and priorities, corrective/preventive/evolutive maintenance process, monitoring and security updates (OPS-04). Out of scope: V2 features (P4).
Subtasks
| # | Subtask | Owner |
|---|---|---|
| 1 | Wave plan by zone with dates, delegates, reseller counts and go criteria per wave | Anis |
| 2 | Training of the remaining delegates and managers per wave (reusing LCH-02 material) | Anis |
| 3 | Import or invitation of the remaining resellers and users per wave; support regions completed | Anis |
| 4 | Promote reseller and delegate apps to the public Play track; store listing review | Imad |
| 5 | Store listing visuals and launch announcement material for resellers | Akram |
| 6 | Reseller web promotion to all resellers: links from the app and invitation landing, announcement | Anis |
| 7 | Capacity watch per wave (API latency, queue depth, DB size, SSE connections) and scaling actions | Anis |
| 8 | Maintenance and support handover: SLA and priority grid, defect reporting channel, warranty period, security update routine | Anis |
Deliverables
- Wave plan and per-wave go/no-go records
- Apps on the public Play track; reseller web announced
- Maintenance and support procedure (SLAs, priorities, contacts) signed by HOCO
Acceptance criteria
- Every zone is open with trained delegates by the end of the last wave (OPS-06)
- Both apps are available on the public Play track (OPS-02)
- The reseller web is live at app.hoco.dz and resellers can sign in with their mobile accounts (RWA-02)
- The maintenance procedure with SLAs and priorities is accepted by HOCO (OPS-04)
Requirements covered
| Requirement | Title | Release |
|---|---|---|
| OPS-03 | Training: administrators and managers, delegates on a full tour scenario, reseller quick guide, admin documentation and support procedures | V1 |
| OPS-04 | Maintenance: warranty period, corrective/preventive/evolutive maintenance, support SLAs and priorities, monitoring and security updates | V1 |
| OPS-06 | Pilot with a limited group of delegates and resellers, then progressive generalisation | V1 |
Test measures
- Per-wave smoke checks and KPI review
- Load check before the largest wave
Risks
- A wave surfaces regional issues (connectivity, GPS, carriers) — keep a pause criterion per wave and a buffer between waves
KPI
- Delivered by Thu 21 Jan 2027 within 1.5 person-day(s).
- Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
- Zero open critical defects, permission gaps or data-integrity regressions at sign-off.
Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.
LCH-04 — Pilot improvements — server & back-office
Prioritised fixes and adjustments from the pilot retrospective; decision log updated.
SRV-29 — V2 API contract — loyalty, packs, credit, returns
Extend packages/contracts with the V2 endpoints first so the mobile V2 work starts against the mock server in parallel.