DQA-02 — Design QA — reseller app build

Screen-by-screen review of the reseller app build against the Claude Design handoff; issues filed with screenshots.

FieldDetails
Task codeDQA-02
PhaseP1 — V1 build & integration
Product scopeV1
StatusPlanned
StartSun 6 Dec 2026
DueMon 7 Dec 2026
ResponsibleAkram — UI/UX designer
Co-responsible—
Effort1 person-day(s) planned · 1.5 from scratch · size S
Area · appDesign QA · design
Depends onMRA-09
Unblocks—
Milestones—

Summary

Screen-by-screen review of the reseller app build against the Claude Design handoff; issues filed with screenshots.

Description

Akram runs a screen-by-screen design review of the reseller app build against the Claude Design handoff once the reseller app features are complete (after MRA-09). Inputs: the staging build (staging flavor) on real devices, the RA frames of design v1.1, the design-system tokens and components, and the 17 Oct decisions. Scope: visual fidelity, states, copy, accessibility and the binding product rules as seen in the UI. Functional bugs found along the way are filed but belong to QA-03. Every issue goes to Imad as a GitHub issue in hoco-mobile with a screenshot, the Claude Design frame link and a severity; the fixes land in Imad's tasks and the accessibility pass MOB-17.

Subtasks

#SubtaskOwner
1Install the staging build on a mid-range 360 dp Android phone and a larger 412 dp phoneAkram
2Review RA-01…RA-36, RA-40 and RA-41 against the frames: spacing and type tokens, colours and pills, icons, component usageAkram
3Check every designed state on device: loading skeletons, empty, error with requestId, offline banner, guest, pending account, forced updateAkram
4Check the binding rules in the UI: no stock quantity anywhere, guest price lock and sign-up prompts, the reseller's customer-type price only, the filter sheet with counts, WhatsApp button placement and region, live status updates, « Envoyée » wording after checkoutAkram
5Copy and formats: final French strings, 1 250,00 DA, dates, business numbers without #, no truncated labelsAkram
6Accessibility: 130 % font scale, TalkBack labels on icon buttons, 48 dp targets, contrast on deviceAkram
7File issues with a screenshot, the Claude Design link, expected vs actual and a severity (blocker, major, minor, polish), labelled design-qaAkram
8Triage session: fix now, after V1, or accepted deviationImad
9Verify the fixes on the next build and close the issuesAkram

Deliverables

  • Design QA issues in hoco-mobile (label design-qa), each with a screenshot, Claude Design link and severity
  • Design QA report for the reseller app: screens reviewed, issues by severity, accepted deviations

Acceptance criteria

  • Every V1 reseller screen has been reviewed on at least two screen widths
  • No blocker or major issue remains open without an agreed fix date
  • None of the 17 Oct rules is broken in the build
  • The accepted deviations are listed and agreed with Imad

Requirements covered

RequirementTitleRelease
NFR-07Accessibility: readable contrast, reachable buttons, consistent text sizes, explicit messagesV1

Test measures

  • Side-by-side comparison of build screenshots with the Claude Design frames for every screen
  • 130 % font scale and TalkBack pass on the ordering path
  • Re-test of fixed issues on the next staging build

Risks

  • The build arrives late and design QA overlaps QA-03 — review the ordering path and onboarding first, then the rest.

KPI

  • Delivered by Mon 7 Dec 2026 within 1 person-day(s).
  • Every acceptance criterion above demonstrated before hand-off; linked requirements' acceptance criteria pass.
  • Zero open critical defects, permission gaps or data-integrity regressions at sign-off.

Generated from content/plan/tasks.json by scripts/generate-team-tasks.mjs. Dates are computed by the scheduler (Sunday–Thursday weeks, holidays excluded) — change the plan, not this page.