Akram — UI/UX designer

Every task assigned to Akram, with dates, dependencies and briefs.

Owns: Design system and every interface, design QA, training and store assets

Load: 36 open tasks · 43.25 person-days at 1 FTE. Each task links to a full brief: description, subtasks, deliverables, acceptance criteria, requirements, screens, API and tests.

18 Oct 2026 → 22 Feb 2027
Oct 2026Nov 2026Dec 2026Jan 2027Feb 202718/1025/101/118/1115/1122/1129/116/1213/1220/1227/123/110/117/124/131/17/214/221/2
Milestones
P0 — Foundations (cadrage, UX/UI, architecture & contract)
P2 — Acceptance, go-live & pilot
P4 — V2 evolutions
AkramV2 scopePublic holiday◆ Milestone (hover for name)

P0 — Foundations (cadrage, UX/UI, architecture & contract)

TaskNamePhaseDatesEffortDepends on
DES-01Day 1 — Kickoff, reference audit & Claude Design setupP0Sun 18 Oct1 d—
DES-02Day 2 — Foundations & design tokensP0Mon 19 Oct1 dDES-01
DES-03Day 3 — Mobile component libraryP0Tue 20 Oct1 dDES-02
DES-04Day 4 — Web & back-office components and page templatesP0Wed 21 Oct1 dDES-02
DES-05Day 5 — Screen inventory validation, user flows & wireframesP0Thu 22 Oct1 dDES-01
DES-06Day 6 — Reseller app: onboarding & accountP0Sun 25 Oct1 dDES-05
DES-07Day 7 — Reseller app: home, search & catalogP0Mon 26 Oct1 dDES-06
DES-08Day 8 — Reseller app: product, cart & checkoutP0Tue 27 Oct1 dDES-07
DES-09Day 9 — Reseller app: orders & financeP0Wed 28 Oct1 dDES-08
DES-10Day 10 — Reseller app: promotions, notifications, account, supportP0Thu 29 Oct1 dDES-09
DES-11Day 11 — Delegate app: access, home, profileP0Mon 02 Nov1 dDES-10
DES-12Day 12 — Delegate app: tour programme, map & POS sheetP0Tue 03 Nov1 dDES-11
DES-13Day 13 — Delegate app: visit, report, prospects, follow-upsP0Wed 04 Nov1 dDES-12
DES-14Day 14 — Delegate app: sign-up, invitation, first order, closingP0Thu 05 Nov1 dDES-13
DES-15Day 15 — Back-office: shell, access & dashboardsP0Sun 08 Nov1 dDES-14
DES-16Day 16 — Back-office: CRMP0Mon 09 Nov1 dDES-15
DES-17Day 17 — Back-office: catalog, pricing & stockP0Tue 10 Nov1 dDES-16
DES-18Day 18 — Back-office: orders, delivery & financeP0Wed 11 Nov1 dDES-17
DES-19Day 19 — Back-office: field ops, promotions, support, reports, adminP0Thu 12 Nov1 dDES-18
DES-20Day 20 — Reseller web: responsive layoutsP0Sun 15 Nov1 dDES-19
DES-21Day 21 — Prototypes, design QA & handoffP0Mon 16 Nov1 dDES-20

21 tasks · 21 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P1 — V1 build & integration

TaskNamePhaseDatesEffortDepends on
DES-22Client feedback round & design revisionsP1Tue 17 Nov → Wed 18 Nov1.5 dDES-21
DES-23Smart notifications design — Notification Centre, action buttons, promotion tabs, flash-sale countdownP1Wed 18 Nov → Thu 19 Nov1 dDES-22
DQA-09Document templates — invoice, delivery note, picking list, receiptP1Thu 19 Nov → Sun 22 Nov1 dDES-22
DQA-10Notification & message copy — push, SMS, email, WhatsApp textsP1Sun 22 Nov → Mon 23 Nov0.75 dDES-22
DQA-01Store assets — icons, splash, screenshots, feature graphicsP1Mon 23 Nov → Tue 24 Nov1 dDES-22
DQA-06Training materials — reseller guide, delegate field guide, admin referenceP1Tue 24 Nov → Wed 25 Nov1.5 dDES-22
DQA-07Field kit — invitation QR flyer & stickerP1Wed 25 Nov → Thu 26 Nov0.5 dDES-22
DES-30V2 designs — loyalty, packs, returns, credit, analytics V2P1Thu 26 Nov → Sun 06 Dec6 dDES-22
DQA-02Design QA — reseller app buildP1Sun 06 Dec → Mon 07 Dec1 dMRA-09
DQA-03Design QA — delegate app buildP1Tue 15 Dec1 dMDA-11
DQA-04Design QA — back-officeP1Wed 16 Dec1 dDSH-12
DQA-05Design QA — reseller webP1Thu 17 Dec0.5 dWEB-05, WEB-06
QA-03Functional test campaign — scripted scenarios on stagingP1Sun 20 Dec → Mon 21 Dec2 dDQA-04, MOB-12, DQA-05

13 tasks · 18.75 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P2 — Acceptance, go-live & pilot

TaskNamePhaseDatesEffortDepends on
DQA-08Pilot UX observation & feedback synthesisP2Thu 31 Dec → Sun 03 Jan2 dLCH-02

1 tasks · 2 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.

P4 — V2 evolutions

TaskNamePhaseDatesEffortDepends on
DQA-12Design QA — V2 surfaces V2P4Sun 21 Feb → Mon 22 Feb1.5 dWEB-20, MDA-20

1 tasks · 1.5 d of open effort. Dates are computed — Sunday–Thursday weeks, holidays excluded.